YMCA of the Rockies Construction Updates

Construction on the grounds of Estes Park Center
February 9, 2009 - Core Developments bulletin
January 26, 2009 - Core Developments bulletin
January 5, 2009 - Core Developments bulletin
December 1, 2008 - Core Developments bulletin
November 12, 2008 - Core Developments bulletin
October 20, 2008 - Core Developments bulletin
October 6, 2008 -  Core Developments bulletin
September 29, 2008 - Core Developments bulletin
Late August, 2008
Circle Drive below the mini golf area and then in from of Sweet Memorial will be roto-milled and paved during the weeks of August 18 and 25.
Dirt work and concrete pouring will also occur at this time behind the Reusch Auditorium.

Early September, 2008
Expect further paving of the main entrance and Circle Drive, concrete pouring on the new Conference Center and form instillation

NOTE: 3-week updates are available in the Administration Building and in your program bulletin.
NOTE: There are no guest laundry facilities during this time.
For Generations to Come
The Core Development Project construction began in January of 2008 with the demolition or relocation of 26 buildings near the area known as staff circle. The old Buildings and Grounds office has been torn down, as has Fairchild dorm and the laundry.

Photo:
The infirmary gets ready to move near the Hempel Auditorium parking lot.